References

Chosen references

Kvaerner Stord AS – Edvard Grieg

Cargotec Finland OY – BMT Cranes

AS Nymo – North Dragon

Aker Egersund AS – Kristin

Offshore references

ClientProjectDescription of worksPlace YearReferences
AS NymoJohan SverdrupPrefabrication of steel structures ~1454 tonsGdańsk2016SEE
Aker Egersund ASMohoPrefabrication of structural steelGdańsk2015SEE
Aker Egersund ASAasta Hansen Prefabrication of structural steel sectionsGdańsk2014SEE
Aker Egersund ASAsgard Subsea Compression Fabrication of structural and outfittingGdańsk2014SEE
AS NymoNorth Dragon
Prefabrication of structural steel sections - project North Dragon Gdańsk2014SEE
Kvaerner Stord ASEdvard GriegFabrication of sections and outfiting (painting and fireproofing included) for the Edvard Grieg Project (~ 3 100 ton)Gdańsk2013 - 2014SEE
Aibel ASTroll A
Prefabrication of structural steel sections - project Troll A (~ 1 200 ton)Gdańsk2012 - 2013SEE
Bladt Industries AS Northwind Offshore Wind FarmPrefabrication of structural steel sections for Topside - Northwind Offshore Wind Farm (~ 500 ton)Gdańsk2012SEE
Aker Egersund ASKristinPrefabrication of structural steel sections for Topside modul - project Kristin (~ 600 ton)Gdańsk2011 - 2012SEE
AkerEgersund ASEkofisk 2/4ZPrefabrication of structural steel sections for Topside - project Ekofisk 2/4Z (~ 2 200 ton)Gdańsk2011 - 2012SEE
Bladt Industries AS Anholt Transformer PlatformPrefabrication of structural steel sections for Topside - Project Anholt Transformer Platform (~ 1 000 ton)Gdańsk2011SEE
Bladt Industries AS London Array Fabrication of 47 pieces of grout skirts for London Array Project (1000 tons - cans + 200 tons - flanges)Gdańsk2011SEE
Aker Kvaerner Stord ASGjøa Semi EPCH Gjøa Semi EPCH Project - fabrication of structural sections and outfittingsGdańsk2007 - 2008SEE
Aker Kvaerner Stord ASH-6e Semi Drilling RigFabrication of temporary lifting structures for H6e projectGdańsk2007SEE
Aker Kvaerner Stord ASH-6e Semi Drilling RigH-6e Semi Drilling Rig Project - Alfa and Beta - 2 setsGdańsk2006 - 2007SEE

Petrochemical references

ClientProjectDescription of worksPlaceYearReferences
Kvaerner Stord ASNyhamnaFabrication of sections and outfiting (painting and fireproofing included) for the Nyhamna Project (~ 1 200 ton of steel + ~200 t of aluminum)Gdańsk2014 - 2015SEE
Grupa Lotos S.A.Spring 2013Overhoul repair and modernization works at refinery "SPRING 2013"Gdańsk Rafinery2013SEE
Grupa Lotos S.A.Spring 2009Stand by repair and modernization works at refinery - "SPRING 2009"Gdańsk Rafinery2009 - 2010 SEE

Grupa Lotos S.A.LPG Washing UnitPiping and Equipment Installation for LPG Washing UnitGdańsk Rafinery2008 - 2009 SEE
SEE
KTI Poland S.A.SRU/TGTConstruction of new "Sulphur Recovery Unit & Tall Gas Treatment" (SRU/TGT)Gdańsk Rafinery2008 - 2009 SEE
SEE
SEE
Grupa Lotos S.A.Storage Tanks V=32 000 m3
Construction of 3 new Storage Tanks V=32.000 m3 eachGdańsk Rafinery2008 - 2009SEE
Grupa Lotos S.A.Spring 2007General ship repair and modernization works at refinery Gdańsk Rafinery2007 SEE
Grupa Lotos S.A.Spring 2005Stand by repair and modernization works at refinery - "SPRING 2005"Gdańsk Rafinery2004 - 2005 SEE
SEE
Grupa Lotos S.A.Installation 900Modernization of installation No. 900Gdańsk Rafinery2004 - 2005 SEE
Grupa Lotos S.A.Tank V= 2 000m3General overhaul of the tank No. 1900-S3; V=2.000 m3Gdańsk Rafinery2004 SEE
Grupa Lotos S.A.Technological feeding installationFabrication of technological feeding installation for
car-cystern terminal
Gdańsk Rafinery2004 SEE
Grupa Lotos S.A.Tank V= 20 000m3Restoration of the tank No. 2080-S124 ; V = 20.000 m3Gdańsk Rafinery2004 SEE
Grupa Lotos S.A.Tank V= 50 000m3Repair of the tank No. 1800-S8 ; V = 50.000 m3Gdańsk Rafinery2004 SEE
Grupa Lotos S.A.Heater no. 900F2Prefabrication and erection of vacuum heater No. 900F2Gdańsk Rafinery2004 - 2005 SEE
Grupa Lotos S.A.PZH-I i PZH-II
Stand by repair and modernization works on Hydrocracking installations: PZH-I i PZH-IIGdańsk Rafinery2003SEE
Grupa Lotos S.A.Car-cysternRepair filling station for car-cysternGdańsk Rafinery2003 SEE
Grupa Lotos S.A.Tank V= 32 000m3Repair of the tank No. 1800-S2 ; V = 32.000 m3Gdańsk Rafinery2003 SEE
Grupa Lotos S.A.Piping 12'' i 14 ''Tank piping renewal - 12 and 14 inches pipelinesGdańsk Rafinery2003 SEE
Grupa Lotos S.A.Tank V= 5 000m3General overhaul of the tank No. 2000-S54 ; V=5.000 m3Gdańsk Rafinery2003 SEE
PERN „Przyjaźń” S.A.Tank V= 50 000m3Repair of the tank No. 10 ; V = 50.000 m3Handling Base in Gdańsk2002 - 2003 SEE

Cranes references

ClientConstructionDescription of worksPlaceYearReferences
Cargotec Finland OY, Kalmar RTG's craneFabrication of RTG's crane with erection parts - 7 set (~ 400 ton) Gdańsk2014SEE
Anchor Contracting ASWater Arches for KMZ fieldMid Water Arches for KMZ field - 3 setsGdańsk2006SEE

Infrastructural references

ClentProjectDescription of worksPlaceYearReferences
VISTAL Gdynia S.A.North Bridge in WarsawFabrication of steel constructions with corrosion protection for North Bridge in WarsawGdańsk2009 - 2010 SEE
Pol-Aqua S.A.WD-4Fabrication and erection of steel Flyover - WD-4 above "Marymoncka" street Warsaw2009 - 2010 SEE
Pol-Aqua S.A.WD-15Fabrication and erection of steel Flyover - WD-15 above "Wybrzeże Gdyńskie" streetWarsaw2009 - 2010 SEE
Pol-Aqua S.A.KP-22Fabrication and erection of steel Footbridge (KP-22) above "Wybrzeże Gdyńskie" street Warsaw2009 SEE

Selected prizes and awards

Eagles in Export of Pomorskie – Most dynamic Exporter

Eagles in Export of Pomorskie –
Best Exporter

Leader of Export 2006

Leader of Export 2005

Forbes, Pomorskie voivodeship – First place in Pomorskie for the most dynamic increase in company value

Gazelles of Business 2008

Gazelles of Business 2007

Leader of Export 2007

Recognition for their commitment and outstanding achievements on the project Edvard Grieg

Leader of Safe Work 2014-2015

Gazelles of Business 2009

The list of awards received:

Eagles in Export of Pomorskie – Most dynamic Exporter – 2015
Eagles in Export of Pomorskie – Best Exporter – 2015
Leader of Safe Work 2014 – 2015
Recognition for their commitment and outstanding achievements on the project Edvard Grieg – 2014
Eagle in Export for fastest growing company – 2014
Eagle on Pomorze 2014
Józef Popławski “Businessman of the Year 2014”
Honorable mention in the competition for the prize Pomeranian “Economic Griffin 2014”
Best Employer in Pomorze of the Year 2014
Best Employer in Pomorze of the Year 2013
Gazelles of Business 2009
Gazelles of Business 2008
Forbes, Pomorskie voivodeship – First place in Pomorskie for the most dynamic increase in company value 2008
Leaders Award of Recognition in the 6th National Ranking of Export Leaders in the category “Certificates and Awards” – 2008
Diploma of Recognition for the President of the Board for Health and Safety – 2008
Gazelles of Business 2007
Leader of Export 2007
Leader of Export 2006
Safety Award for the design of Asgard “B” from Kvaerner Oil & Gas AS – 2005